Completing infrastructure for new streets at Ifraz 35, Hay Al-Hakim
Delivering the core infrastructure works for the new streets at Ifraz 35, including sanitation networks, rainwater drainage, GIS mapping systems, and water and electricity extensions.
Project data
- Location
- Ifraz 35, Hay Al-Hakim, Basra
- Completion year
- 2024
- Status
- Completed and handed over
- Scope
- Sanitation · rainwater drainage · water and electricity extensions
- Documentation
- GIS mapping systems
- Completion certificate
- Available on request
The completion certificate is available on request for prequalification purposes.
Site photography
Photographs from the company's own execution on site, documented with date and location.

Laying the main water line
Ifraz 35, Hay Al-Hakim, Basra2024

Excavating the network trenches in the neighbourhood
Ifraz 35, Hay Al-Hakim, Basra2024

Delivery of DN 800 GRP pipes
Ifraz 35, Hay Al-Hakim, Basra2024

Pipe laying and backfill around the line
Ifraz 35, Hay Al-Hakim, Basra2024

Hoisting the steel network pipe
Ifraz 35, Hay Al-Hakim, Basra2024

Excavating the services trench along the new road
Ifraz 35, Hay Al-Hakim, Basra2024

Sand backfill over the geotextile-wrapped pipes
Ifraz 35, Hay Al-Hakim, Basra2024

Installing a sewer manhole chamber
Ifraz 35, Hay Al-Hakim, Basra2024
The challenge
New streets are routinely handed over with undocumented networks, then dug up repeatedly because nobody knows where the lines were laid. The requirement wasn't only to lay a network, but to hand over a district ready for urban expansion with documentation that lets the client actually manage it afterwards.
The approach
We executed the sanitation and rainwater drainage networks within a single scope, rather than splitting responsibility across multiple parties.
We documented the networks with GIS mapping systems handed over with the project — something most local contractors skip.
Core water and electricity extensions were delivered to make the district ready for habitation and sustainable urban development.
The outcome
The district was handed over in 2024 with cartographically documented networks and full readiness for habitation and expansion.
Request this project's completion certificate
We send this project's completion certificate on request for prequalification purposes. And if you have a project of similar scope, send us the bill of quantities or a scope description and we'll come back with a proposal covering specifications, schedule and price.
We reply Sunday – Thursday, 8:00 – 16:00 Baghdad time
Related projects

Integrated infrastructure development: paving and sanitation in Ajaydin and Hay Al-Hakim
Ajaydin and Hay Al-Hakim, Basra2023
Sanitation networks, rainwater pumping stations, and modern road paving with high-quality Italian coverings, improving quality of life and traffic movement across two residential areas.
Project details

Building two model schools in Basra city centre
Basra city centre2024
Two model schools with contemporary architectural design, executed in partnership with Chinese firms, with reinforced concrete skeletons and high-efficiency infrastructure.
Project details