Integrated infrastructure development: paving and sanitation in Ajaydin and Hay Al-Hakim

Sanitation networks, rainwater pumping stations, and modern road paving with high-quality Italian coverings, improving quality of life and traffic movement across two residential areas.

Project data

Location
Ajaydin and Hay Al-Hakim, Basra
Completion year
2023
Status
Completed and handed over
Scope
Paving · sanitation · rainwater pumping stations
Coverings
High-quality Italian coverings
Completion certificate
Available on request

The completion certificate is available on request for prequalification purposes.

Site photography

Photographs from the company's own execution on site, documented with date and location.

  • Street 5 in Hay Al-Hakim before and after paving

    Street 5 — before and after paving

    Ajaydin & Hay Al-Hakim, Basra2023

  • Hay Al-Hakim streets before and after paving

    Hay Al-Hakim streets — before and after

    Ajaydin & Hay Al-Hakim, Basra2023

  • Grading and preparing the streets with company equipment

    Grading and preparing the streets before paving

    Ajaydin & Hay Al-Hakim, Basra2023

  • Company-owned Caterpillar grader during levelling works

    Levelling with the company's own equipment

    Ajaydin & Hay Al-Hakim, Basra2023

  • Casting concrete kerbs along the streets

    Casting concrete kerbs along the streets

    Ajaydin & Hay Al-Hakim, Basra2023

  • Asphalt paver and roller laying the road surface on site

    Paving with specialised equipment — paver and roller

    Ajaydin & Hay Al-Hakim, Basra2023

  • Trenching and laying a large sewer pipe in Hay Al-Hakim

    Laying the sewer line in Hay Al-Hakim

    Ajaydin & Hay Al-Hakim, Basra2023

  • Workers laying interlock paving in a narrow residential lane

    Interlock paving in a residential lane

    Ajaydin & Hay Al-Hakim, Basra2023

  • Ajaydin streets after paving was completed

    Ajaydin streets after paving

    Ajaydin & Hay Al-Hakim, Basra2023

The challenge

Paving over a new network settles within months if the backfill isn't compacted properly — and then the dispute starts between the network contractor and the paving contractor. Splitting the work between two parties is the cause of the problem, not its consequence.

The approach

  • We executed the network, compaction, and paving within one scope under one responsibility — so there is no dispute about who owns the first settlement.

  • Rainwater pumping stations were installed to address water pooling, the hardest problem in Basra drainage.

  • High-quality Italian coverings were used as the contract specified, not a local equivalent.

The outcome

Completed in 2023 with integrated paving and sanitation across two residential areas, and pumping networks addressing rainwater pooling.

Request this project's completion certificate

We send this project's completion certificate on request for prequalification purposes. And if you have a project of similar scope, send us the bill of quantities or a scope description and we'll come back with a proposal covering specifications, schedule and price.

We reply Sunday – Thursday, 8:00 – 16:00 Baghdad time

Related projects